Fact vs. Fiction: Black Mountain's "Quiet, Low-Impact" Pitch to Parker County

📘 Summary

Parker County residents have started receiving requests from Black Mountain, the Fort Worth oil-and-gas developer behind the roughly 2,000-acre Pearson Ranch data center site north of Weatherford. The requests point to a pre-written letter for "local lawmakers" that takes 30 seconds to send and promises a "quiet, low-impact facility" that will bring "real tax relief," good jobs and a closed-loop water system that uses "less annually than a typical car wash or laundromat."

We checked the pitch against state and local records. Here's the short version:

  • Confirmed: Black Mountain already holds a state air permit for five natural-gas turbines (75 MW) at 501 Pearson Ranch Road, authorized to run all 8,760 hours of the year. The company's own filing estimates about 137 tons of air pollutants a year, including 41 tons of VOCs and 24 tons of NOx. The letter never mentions turbines, gas or emissions.
  • Reported, not yet filed: The district's general manager said at its Aug. 27 board meeting that Black Mountain intends to request 138 million gallons of groundwater a year, as our Sept. 5 briefing reported. No formal application appears in the district's posted records yet. If the request comes in at that size, the "car wash" comparison is off by a wide margin.
  • Unsubstantiated: Black Mountain has published no tax revenue estimate, no permanent jobs number, and no plan showing how it will connect to the grid. Parker County has adopted a policy against tax abatements for hyperscale data centers.
  • Worth knowing before you click "send": The form requires your name, email, phone and home address, and the fine print opts you into "autodialed and automated calls and texts" from Black Mountain. Anyone in any state can send the letter.

⚖️ The Pitch vs. the Record

Where the record supports a claim, we say so. Where nothing public confirms or rules it out, we say that too.

Black Mountain saysWhat the record showsStatus
"A quiet, low-impact facility"Five 15 MW gas turbines permitted to run 24/7, with about 137 tons a year of emissions. Commissioners raised noise concerns for neighbors and livestock on May 26.Misleading — leaves out an on-site power plant
Closed-loop water that uses "less annually than a typical car wash or laundromat"The district GM reported an intended request of 138 million gallons a year. That's roughly the water of 40 busy car washes combined. No Black Mountain water figure has been published.Contradicted if the 138M request is filed; not yet confirmed in a filing
"Millions" in tax revenue "without raising taxes on homeowners"No revenue estimate published. The county won't grant abatements, so new property value would be taxed, but Texas school finance offsets much of a district's new local value with lower state aid.Cannot be confirmed or denied — no numbers released
Local trade jobs and a Weatherford College partnershipConstruction work is likely. Permanent staffing hasn't been disclosed, and we found no public Weatherford College announcement.Cannot be confirmed or denied
"Won't hike up my electric bills" and will "strengthen our power infrastructure"The turbines are registered as "backup / bridge power for a new data center," not for the public grid. No grid connection filing for the site has been made public.Cannot be confirmed or denied

What the pitch gets right, or could

  • The turbines meet a strict NOx standard. The permit requires 0.14 pounds of NOx per megawatt-hour or less, with catalytic controls on every unit. Per unit of power, that is clean for gas. The problem is the total: running all year still adds up to 24 tons. (Confirmed)
  • New taxable value is real. With no abatement on the table, the land and buildings would go on the tax rolls at full value. How much reaches schools or lowers anyone's bill is unknown. (Partly confirmed)
  • Closed-loop cooling uses far less water than evaporative cooling. If Black Mountain builds it that way, consumption would be much lower than an open, evaporative design. But closed loops still need fill and makeup water, and the turbines need water too. (Plausible, unconfirmed)
  • Construction jobs. A project this size would employ trades for a time. (Likely, no number given)

What the pitch leaves out

  • A 24/7 gas power plant with about 137 tons a year of emissions, in a county that is already part of the federal Dallas–Fort Worth ozone nonattainment area. (Confirmed)
  • A groundwater draw of up to 138 million gallons a year, about 378,000 gallons every day. (Reported, not yet filed)
  • Who Black Mountain is: an oil-and-gas company running the same buy-land, file-for-turbines approach at sites across Texas. (Confirmed)
  • Any hard numbers on taxes, jobs, total power demand or water. (Not disclosed)

💨 The Air Permit

Texas Commission on Environmental Quality records show Black Mountain's power plant cleared in 21 days. The application from Fort Worth Power Core LLC was received March 13, 2025, and approved April 3, 2025, as registration No. 179422, the "Parker Plant." TCEQ filings list Black Mountain CEO Rhett Bennett as the responsible official, with a blackmtn.com email address.

It went through TCEQ's standard permit for electric generating units, a streamlined track that, unlike a major-source permit, generally skips the public notice and comment process. (Our Data Center Near You guide explains how those tracks differ.) TCEQ's technical review describes five simple-cycle Siemens SGT-400 turbines, 15 MW each, that "will provide backup / bridge power for a new data center and will be limited to 8,760 hours per year." That is every hour of the year.

Here is what the company's consultant estimated the turbines would emit at full operation:

PollutantTons per year
Particulate matter (PM/PM10/PM2.5)41.4
Volatile organic compounds (VOCs)41.2
Nitrogen oxides (NOx)24.1
Carbon monoxide15.3
Ammonia (from the pollution controls)12.9
Sulfur dioxide2.0
Total136.9

Those are estimates from the March 2025 application, not measurements, and they assume year-round operation. NOx and VOCs matter in particular because they are the two ingredients of ground-level ozone, and Parker County is one of nine counties in the federal Dallas–Fort Worth ozone nonattainment area. In December 2025, Fort Worth Power Core told TCEQ the permitted activity was "operational." That may mean only that the authorization is in use. Whether the turbines are built or running cannot be confirmed from public records.

The same LLC holds TCEQ registrations for 14 other power plant sites, from Bowie County to Williamson County, including three in Tarrant County. Gas turbines as "bridge power" for data centers are becoming a statewide pattern; see The Biggest Polluter for the largest example yet.

💧 The Water Question

According to the Upper Trinity Groundwater Conservation District's general manager, Doug Shaw, Black Mountain has told the district it intends to request 138 million gallons of groundwater a year. Shaw said so at the district's Aug. 27 board meeting, which we covered in our Sept. 5 briefing. We checked again for this post: no formal application from Black Mountain or Fort Worth Power Core appears in any hearing notice, agenda or minutes the district has posted through its Oct. 15, 2026 meeting. The district's September and October agendas do include a general manager's report on "high-volume groundwater production permit applications," without naming applicants.

A request that size would require a hydrogeologic study under rules the district adopted this year, modeling impacts on neighboring wells at 1, 10, 30 and 50 years, and nearby landowners could request a contested-case hearing. Our Data Center Near You guide walks through how that process works.

What 138 million gallons a year looks like

Compared with138 million gallons a year equals
Every single dayAbout 378,000 gallons
Texas single-family homesAbout 1,670 homes' water for a full year (227 gallons per home per day, TWDB)
Parker County householdsAbout 3% of the county's 56,437 households
Texas residents at homeAbout 4,300 people (88 gallons per person per day, TWDB)
Conveyor car washes4.6 million washes a year, or about 12,600 cars every day (30 gallons of fresh water per car)
A busy car washAbout 40 of them combined, each washing 300 cars a day, every day (our assumption for illustration)
HotelsAbout 3,700 rooms occupied year-round (102 gallons per room per day, ENERGY STAR)
OfficesAbout 29,000 office workers (13 gallons per worker per day, ENERGY STAR)
The land424 acre-feet: 424 acres under a foot of water
The district's largest recent approvalAbout 6 times the 22.1 million gallons a year approved for a Weatherford subdivision in May

We couldn't find a reliable published benchmark for school water use, so we left schools out rather than guess. If the request is filed at 138 million gallons, a "typical car wash or laundromat" isn't a fair comparison.

💰 Taxes, Jobs, Bills and Noise

Taxes. On June 9, 2026, the Parker County Commissioners Court adopted a resolution setting county policy against property-tax abatements for hyperscale data centers. It also called for independent reviews of grid and water impacts and opposed open-loop evaporative cooling in water-short areas. Any "real tax relief" would have to come from new taxable value alone, and Black Mountain hasn't published an estimate. For schools, Texas's funding formulas offset much of a district's new local property value with reduced state aid. A data center doesn't turn into classroom dollars one-for-one. Our guide's tax section covers what to ask. (Cannot be confirmed or denied.)

Jobs. Construction would bring trade work for a time. Black Mountain hasn't said how many permanent jobs the site would hold, and we found no public announcement from Weatherford College about a partnership. (Cannot be confirmed or denied.)

Electric bills. The turbines exist to power the data center itself. Nothing public shows how or when the site would connect to ERCOT, or who would pay for any transmission upgrades. (Cannot be confirmed or denied.)

Noise. Commissioners discussed noise and quality-of-life impacts on neighbors and livestock when the land purchase came up on May 26. Gas turbines permitted to run around the clock are hard to call "quiet."

🏢 Who Is Behind It

Black Mountain is a Fort Worth energy company with oil-and-gas roots, now assembling "powered land" for hyperscale data centers. It is led by CEO Rhett Bennett and backed by credit financing from Elda River Capital Management, announced in December 2025. In Fort Worth, a rezoning vote on 80 more acres for its $10 billion southeast campus has been pushed to December. Reporting this year has tied the company to sites in Fort Worth, Parker County, Bowie County and San Antonio.

In Parker County, Black Mountain Power LLC has assembled about 2,000 acres around 501 Pearson Ranch Road, near Lake Weatherford. The air permit is held by Fort Worth Power Core LLC, which shares Black Mountain's Fort Worth address and CEO.

🧭 What Parker County Residents Can Do

  • Ask the groundwater district. The Upper Trinity GCD board meets monthly in Springtown and by Zoom; its next hearing is Thursday, Oct. 15, at 5 p.m. Ask whether a Black Mountain application has been filed. Contested-case requests and comments go to General Manager Doug Shaw at doug@uppertrinitygcd.com or P.O. Box 1749, Springtown, TX 76082.
  • Ask TCEQ. TCEQ's Region 4 office (817-588-5800) covers Parker County. Ask whether the Parker Plant turbines (registration 179422) are built or operating, and report emissions or noise problems there.
  • Read the fine print before you sign. Black Mountain's letter shares your contact details with the company and signs you up for automated texts and calls.
  • Follow the county. Ask commissioners what state agencies have said in response to the June 9 resolution.

Our Data Center Near You guide has a full checklist, contacts and the records to request.

🧾 Conclusion

Black Mountain's letter isn't wrong about everything. A closed-loop design would save water, the turbines do meet a tight NOx standard, and a project this size would add taxable value. But the letter asks residents to vouch for a "quiet, low-impact facility" while leaving out the only facts state records confirm: a 75-megawatt gas plant permitted to run every hour of the year, and plans for up to 138 million gallons of groundwater annually. The tax relief, the jobs and the stable electric bills are promises without numbers. Residents deserve those numbers before they're asked to sign anything.

For more analysis on Texas energy and AI, visit PowerGrabTX.com.

Sources

  • Black Mountain campaign page via causetxt.org/wg5519 (redirects to Speak4) — reviewed October 10, 2026; nothing submitted
  • TCEQ Central Registry — Fort Worth Power Core LLC (CN606278281) and Parker Plant (RN112172408)
  • TCEQ Records Online — Registration 179422: standard permit application and emissions calculations (March 2025), technical review (April 3, 2025), 2025 Annual Operational Status Report (December 10, 2025); search RN112172408
  • TCEQ — "Dallas-Fort Worth: Current Attainment Status"
  • Upper Trinity Groundwater Conservation District — 2026 meeting agendas, minutes and recordings, including the Oct. 15 agenda and May 18 minutes
  • Citizen Portal — "At a glance: Parker County actions on data-center concerns (June 9, 2026)"
  • Citizen Portal — "Groundwater district warns large permits trigger in-depth studies and contested cases"
  • Springtown Epigraph — "No action regarding proposed data center"
  • CNHI News — "Grassroots group concerned about data centers draws more than 100 to information meeting"
  • IREI — "Black Mountain Power secures financing from Elda River to advance Texas data center strategy"
  • Texas Water Development Board — "Water Use of Texas Water Utilities" (household and per-person use)
  • U.S. Census Bureau — QuickFacts: Parker County, Texas
  • International Carwash Association — "Water Use, Evaporation and Carryout in Professional Car Washes"
  • ENERGY STAR — "DataTrends: Water Use Tracking" (hotel and office benchmarks)

Related Pages

Other Posts

AI data centers are reshaping Texas faster than most people realize. If you want to stay ahead of the changes affecting your community, energy costs, and local environment, join our update list.

Stay informed about AI's impact in Texas